Bid recap: labor USD 18,000, materials USD 42,500, equipment USD 6,200, subcontracts USD 15,000. Overhead is 12 percent of those directs. Profit is 10 percent of total cost. What is the bid, to the nearest dollar?
- AUSD 91,504
- BUSD 98,824
- CUSD 100,654
- DUSD 108,824