Before a well rig may be set up to drill, plug, or rehabilitate a well, NAC 534.320 requires what?
- AOnly a verbal call to the county building department
- BOnly a posted card on the property fence
- CNo filing if the well is for domestic use
- DA notice of intent submitted to the Division and Division approval of that notice