On-site cut will yield 4,500 bank cubic yards. That soil shrinks 10 percent from bank to compacted measure. The job needs 4,000 compacted cubic yards of fill. After placing all of the cut in the fill, what is the result?
- AA surplus of about 50 compacted cubic yards
- BA borrow need of 500 compacted cubic yards
- CA surplus of 500 bank cubic yards with no conversion required
- DThe cut and fill are exactly balanced with no surplus