On an NMDOT hot-mix asphalt overlay, what is the primary purpose of a tack coat?
Bituminous Surface Treatments And Pavement
Question · Easy
How deep before you need a trench box?
Short
Per NMDOT 2019 Section 423.3.5.1, the Contractor shall not place hot-mix asphalt on which of the following surfaces?
Per NMDOT 2019 Section 423.3.5.1, HMA may be placed when the Chill Factor is at least which value and rising?
Trades Exam Prep Podcast
Listen on Spotify
Podcast
Per NMDOT 2019 Section 423.3.5.1, when the air temperature is 60 °F or warmer, how is Chill Factor treated for HMA placement?
Per NMDOT 2019 Section 423.3.5.2, what may be used to keep HMA from sticking to roller wheels?
Per NMDOT 2019 Section 407.3.4, the Project Manager sets the tack-coat spray rate to provide what residual asphalt-cement content?
Question · Medium
Per NMDOT 2019 Section 423.3.5.4, longitudinal joints in successive HMA courses shall be offset at least how far from the joint in the underlying course?
Per NMDOT 2019 Section 423.3.5.4, where shall the Contractor avoid placing HMA longitudinal joints unless the Project Manager approves otherwise?
Per NMDOT 2019 Section 423.3.5.4, unless otherwise specified, a transverse HMA joint shall have at least which taper?
When paving under traffic, NMDOT 2019 Section 423.3.5.4 limits how long a tapered longitudinal HMA joint may remain exposed. What is that limit?
Per NMDOT 2019 Section 423.5, Accepted HMA is paid by which pay units?
Per NMDOT 2019 Section 407.5, Asphalt Material for Tack Coat is paid by the:
A common HMA yield check used in the Hot-Mix Asphalt Paving Handbook and state paving inspection is that 110 pounds per square yard equals about how much compacted thickness?
According to the Hot-Mix Asphalt Paving Handbook compaction sequence, where should the breakdown roller operate?
Which bituminous treatment is a light application of diluted emulsion used to seal a weathered asphalt surface, not to bond a new overlay?
Per NMDOT 2019 Section 408, a prime coat is applied to which surface?
Per Asphalt in Pavement Maintenance (MS-16), interconnected fatigue cracks that form a chicken-wire or alligator pattern usually indicate which condition?
A chip seal (bituminous surface treatment) consists of which combination?
Per NMDOT 2019 Section 424, warm-mix asphalt may be placed when the Chill Factor is at least which value and rising?
A 12-foot travel lane is to be paved 1 mile long with 2 inches of compacted dense-graded HMA. Using 110 lb per square yard per inch, how many tons of mix are required (no waste)?
Question · Hard
A rectangular parking lot 200 ft by 150 ft will receive 3 inches of compacted dense-graded HMA. Using 110 lb per square yard per inch, how many tons are required (no waste)?
A paver covers 2,400 square yards with 180 tons of dense-graded HMA. Using 110 lb per square yard per inch, what compacted thickness does that yield indicate?
NMDOT 2019 Section 423.3.5.4 requires a transverse HMA joint taper of at least 3 ft at a slope no steeper than 24:1. What is the maximum vertical drop over that 3 ft taper?
An NMDOT overlay will be tacked at a residual asphalt-cement rate of 0.06 gal/SY over 8,000 SY. The emulsion is 50 percent residual asphalt. How many gallons of undiluted emulsion are required (no waste)?
Under current NMDOT Superpave mix designations, an SM-12.5 surface mix has which nominal maximum aggregate size?
Per NMDOT 2019 Section 203.2.1.2, unclassified excavation consists of:
Earthwork
Per NMDOT 2019 Section 203.2.1.3, borrow is Contractor-provided suitable embankment material obtained from:
Per NMDOT 2019 Section 203, roadbed embankment material shall be placed in uniform lifts not exceeding:
Per NMDOT 2019 Section 203.3.6, each layer of embankment shall be compacted to at least what percentage of maximum dry density by AASHTO T 180 (Modified Proctor)?
Per NMDOT 2019 Section 203.3.6, for soils that are not high-plasticity (PI less than 15), in-place moisture at compaction shall be:
Per NMDOT 2019 Section 203.3.6, for soils with a plasticity index of 15 or greater, moisture at compaction shall be:
Per NMDOT 2019 Section 203.2.1.1, material is classified as rock excavation by the seismic test when seismic velocity is greater than:
Per NMDOT 2019 Section 203.2.1.1, boulders or detached stones are rock excavation by the handling test when they have a volume greater than:
Per NMDOT 2019 Section 303, Base Course shall be compacted to at least what percentage of maximum density by AASHTO T 180, Method D (TTCP Modified)?
Per NMDOT 2019 Section 303.3.3, the Base Course surface tolerance shall not exceed:
Per NMDOT 2019 Section 203.5, Unclassified Excavation and Borrow are paid by the:
When NMDOT pays earthwork on the final cross-sectioned volume, how are shrinkage and swell handled?
A roadside slope shown as 2:1 (H:V) means:
A rectangular cut is 300 ft long, 24 ft wide, and 2 ft deep. What is the bank volume in cubic yards?
Using the average-end-area method, a 50-foot station has end areas of 45 ft² and 75 ft². What is the volume?
A fill needs 2,000 compacted cubic yards. The borrow soil shrinks 20 percent from bank to compacted volume. How many bank cubic yards must be excavated?
A rock cut measures 800 bank cubic yards. If the rock swells 25 percent when blasted and loaded, how many loose cubic yards must be hauled?
A roadway template is 24 ft wide at subgrade. Both side slopes are 2:1 (H:V) in an 8-ft-deep cut through level ground. What is the top width of the cut?
Cross-section areas at Station 10+00 and Station 11+00 are 120 ft² and 80 ft². Using average end area over the 100-ft station, what is the volume?
On-site cut yields 4,500 BCY of soil that shrinks 10 percent. The project needs 5,000 CCY of embankment. How much additional borrow (bank cubic yards) is required if the borrow also shrinks 10 percent?
Before non-emergency excavation in New Mexico, the excavator must give New Mexico One Call (811) advance notice of at least: