What passing score does NMAC 14.6.3.8 and the PSI New Mexico Contractor Examinations Candidate Information Bulletin require on the Business and Law Examination?
Licensing Requirements
Question · Easy
Final walkthrough: the punch list
Short
Under NMAC 14.6.3.8, a qualifying-party certificate may be issued only to an individual who is at least:
Which statement about a New Mexico CID contractor license is correct under NMAC 14.6.3.8 and NMSA 1978 Section 60-13-18?
Trades Exam Prep Podcast
Listen on Spotify
Podcast
A licensed New Mexico contractor wants to bid using a trade name that is not the name shown on the CID license. What does NMAC 14.6.3.8 require?
What proof of financial responsibility must a New Mexico contractor furnish at initial licensure and as a condition of each renewal?
Why a balance sheet balances
Before an applicant may sit for a New Mexico qualifying examination, NMAC 14.6.3.8 generally requires documented work experience of:
Question · Medium
How does NMAC 14.6.3.8 credit accredited technical training toward the qualifying-party experience requirement?
Payment from the New Mexico contractor license bond required by NMSA 1978 Section 60-13-49 is used to:
A CID inspector issued a final inspection on March 1, and the local building official issued a certificate of occupancy on April 15 of the same year. Under NMAC 14.6.3.8, a claim against the contractor's USD 10,000 license bond must be made within:
Question · Hard
Six feet: a hard-hat anthem
A qualifying party wants to qualify two separate New Mexico licensed entities that are not a joint venture. What common-ownership rule applies under NMAC 14.6.3.8?
If a New Mexico licensee loses its qualifying party through termination or otherwise, who must notify CID and by when?
An incomplete New Mexico contractor application is received by CID on January 10. If the remaining requirements are not completed, when does the application expire and what happens to the fees?
A candidate passes the New Mexico Business and Law exam on June 1. According to the PSI bulletin, how long is that passing score valid, and how does it relate to the trade exam?
The longest way home
A new qualifying-party certificate is issued after the exam score is reported to CID, but the individual never attaches it to a valid license. When does that new certificate automatically expire?
For the New Mexico Business and Law exam (not an inspector exam), what retest limit does the PSI bulletin impose?
What happens to a New Mexico sole proprietor's contractor license on the death of the sole proprietor?
What is the primary purpose of a quantity takeoff when preparing a construction bid?
Estimating And Bidding
OSHA fall heights, to scale
A public owner requires a bid bond with each proposal. What is the bid bond's primary purpose?
An addendum issued two days before bid opening changes the specified roof membrane. What should a bidder do?
A takeoff shows 2,400 square feet of gypsum board. The estimator adds a 10 percent waste factor. How many square feet should be purchased?
A unit-price bid item is 285 square yards of concrete paving at USD 84 per square yard. What is the extended amount for that item?
Direct costs on a job are USD 50,000. The estimator applies 15 percent overhead to direct cost, then applies 10 percent profit to the subtotal. What is the bid amount?
A contractor's annual overhead is USD 180,000. Estimated annual direct-cost volume is USD 1,200,000. What overhead amount should be assigned to a job with USD 64,000 of direct cost if overhead is allocated as a uniform percentage of direct cost?
After opening bids, a general contractor discloses a subcontractor's quoted price to a competitor and asks that competitor to beat it. This practice is commonly called:
On a public bid, what is the difference between a responsive bid and a responsible bidder?
An estimate shows materials USD 22,500, labor USD 16,800, and equipment USD 4,200. The contractor applies a combined 18 percent markup for overhead and profit on those direct costs. What is the bid?
Which business form generally exposes the owner to unlimited personal liability for business debts?
Business Organization And Financial Management
Which equation must a balance sheet satisfy?
Under the accrual method, when does a contractor recognize revenue on a progress-billed contract?
Working capital is best defined as:
A contractor reports current assets of USD 198,000 and current liabilities of USD 90,000. What is the current ratio?
A contractor has current assets of USD 315,000 and current liabilities of USD 210,000. What is working capital?
A USD 400,000 contract holds 10 percent retainage. The first pay application is for 40 percent completion with no previous billings. How much should the contractor expect to receive if the application is approved as submitted?
A contractor's year shows contract revenue of USD 625,000 and job costs of USD 437,500. What is the gross-profit percentage?
In double-entry bookkeeping, every transaction is recorded with:
What is the main purpose of job-cost accounting for a contractor?
Depreciation of a construction truck is best described as:
A contractor's fixed annual overhead is USD 96,000. Average contribution margin is 24 percent of revenue. What annual revenue is required to break even?
A job is bid at USD 185,000. Actual direct costs are USD 142,000 and allocated company overhead is USD 21,300. What is net profit on the job?
Under NMAC 14.6.3.8, a New Mexico contractor license is issued only to:
A surety reviews two contractors. Contractor A has a current ratio of 0.70. Contractor B has a current ratio of 2.10. What is the most accurate interpretation?
A contractor is 50 percent complete on a USD 240,000 contract with 10 percent retainage. Stored materials of USD 12,000 are billable this period in addition to the percent-complete amount, and retainage also applies to stored materials. There were no prior billings. What is the net payment due?