Before steel erection begins, OSHA 1926.752 requires written notification that footing, pier, and wall concrete has attained:
- A75 percent of the intended minimum compressive design strength, or enough strength to sup…
- B10 percent of design strength from a laboratory-cured cylinder only
- CAny strength, as long as the forms have been stripped
- D100 percent of 28-day strength plus 7 additional days