A revetment requires a riprap blanket 120 ft long, 15 ft up the slope face, and 1.5 ft thick. How many cubic yards of riprap are required before waste, and how many cubic yards if 20 percent additional material is added for voids, overlap, and placement loss?
- A67 cy before waste; 80 cy with 20 percent extra
- B100 cy before waste; 120 cy with 20 percent extra
- C180 cy before waste; 216 cy with 20 percent extra
- D2,700 cy before waste; 3,240 cy with 20 percent extra