A contractor estimates that a three-person crew can apply scratch coat to 300 square feet of wall per day. For a 2,400-square-foot project, how many crew-days are needed for the scratch coat alone?
- A6 crew-days
- B10 crew-days
- C12 crew-days
- D8 crew-days