Estimate concrete for ten cylindrical holes, each 12 inches in diameter and 36 inches deep. Ignore post displacement and overbreak, then add the specified 15% allowance. What is the approximate volume?
Planning And Estimating
Question · Hard
OSHA noise limits
Short
What is the key scope boundary of California's C-13 Fencing Contractor classification?
Planning and Estimating
Flashcard
A straight fence follows a uniform 15% grade over a horizontal plan distance of 200 feet. What is its approximate length along the slope?
Question · Medium
Kind of request a contractor submits so control staking can be laid out before fence work begins.
Preconstruction documents
Guess the Term
Cheat sheet
An open, straight 350-foot chain-link run has an end post at each end, no gates, and 10-foot post bays. Fabric comes in 50-foot rolls with no allowance. How many rolls and interior line posts are needed?
Read the clue and guess the term in 6 tries.
Game
A straight open fence run is 73 ft long with a specified maximum bay of 8 ft. How many posts are needed?
Four cylindrical holes are each 16 inches in diameter and 42 inches deep. A specified bag yields 0.45 cubic foot. Ignoring post displacement and waste, what is the minimum whole-bag quantity?
Kind of item that is a work unit a contractor prices in a construction contract.
An adopted project specification uses the CLFMI template limit for chain-link line-post intervals, with no stricter project requirement. What maximum spacing does that template state?
Question · Easy
Six feet: a hard-hat anthem
How much concrete is estimated for ten 12-in-diameter, 36-in-deep cylindrical holes with 15% allowance?
The building department confirms that a proposed ordinary fence is exempt from a building permit. Which conclusion is correct when planning its location and height?
Line, end, corner or gate member that supports chain-link fabric and is set in a concrete footing.
Site preparation
In the March 2017 CLFMI framework specification, which description identifies Group IA pipe rather than confusing framework with fabric or solid stock?
Swap tiles to line up three of the same term.
Term Match
A grade-following fence has a 200-ft horizontal run and uniform 15% grade. What is its sloping length?
A takeoff calls for 1,000 usable cedar pickets. The estimator explicitly allows another 100 to 150 pickets for cuts and rejected pieces. What allowance, relative to the usable quantity, is being applied?
Set a fence post exactly vertical.
Before setting a fence near a disputed property boundary, what provides the appropriate basis for establishing its alignment?
OSHA fall heights, to scale
A detail places tension bands at both ends of a 60-in attachment length, with spacing no greater than 12 in. How many bands are needed per pull?
For an enclosure governed by California Health and Safety Code section 115923, what is the maximum vertical clearance between the ground and the bottom of the enclosure?
Verb for what utility owner/operators do to confirm where their buried installations are before excavation starts.
A 120-foot wood fence has three continuous horizontal rail lines. Rails come in 16-foot boards. Each rail line is estimated separately, and no offcuts may be reused between lines. What is the minimum board count, ignoring saw kerf and other waste?
Flip two cards at a time to find matching terms.
Term Pairs
Which site constraints must be resolved before laying out a proposed fence line?
A security design selects the smallest opening among the following chain-link fabrics to reduce available handholds and footholds. Which mesh fits that selection?
Interlaced steel sheet that hangs between posts and is specified by coating class and wire size.
Installation and repair
A double-swing gate has a 20-foot clear opening between posts. The approved layout reserves a total of 6 inches for both hinge offsets and the center gap. What width is required for each of two equal leaves?
What must a chain-link fabric specification distinguish about gauge and polymer coating?
An estimator wants material cost per linear foot for a fence package. Which calculation has the correct units?
Wire-thickness number: 11 for chain-link 84 inches or less tall, 9 for taller or slatted fences.
Site information indicates hard rock at the specified posthole locations. Which estimating action best addresses that known condition?
Find five hidden terms in a grid of letters.
Term Search
For a normal California home-improvement fence contract, how do the written-contract and deposit rules work?
An owner proposes adding privacy slats to an existing open chain-link fence. What design issue should the contractor raise before pricing the change?
Openings between crossed wires in chain-link, counted per fence height as the diamond count.
For a nonemergency posthole excavation in California, which notification plan meets the ordinary Government Code section 4216.2 timing rule?
Preparation And Post Installation
What are the normal California 811 timing and ticket requirements before a contractor excavates fence postholes?
Preparation and Post Installation
An approved site-specific fence drawing requires a 36-inch-deep, 12-inch-diameter line-post footing. Unexpected loose fill is found. What should occur before concrete is placed in a proposed shallower hole?
Kind of wire that must meet ASTM A121 and carry two-point projections.