If a job site requires 5,000 bank cubic yards of cut and has 5,000 bank cubic yards of fill needed, but the excavated earth swells by 20% loose and shrinks by 10% when compacted, what is the net earth balance?
- AExact balance zero import
- BSurplus of 500 cubic yards
- CShortage of 556 cubic yards
- DSurplus of 1,000 cubic yards