During Nexus Sprint Planning, all teams have selected their work and plan to begin. A team realizes the sequencing of dependent work items makes it impossible to finish integration by Sprint end. What should the teams do?
- AProceed and raise the issue at the Nexus Sprint Review
- BRemove the dependent items from the Sprint and inform the Product Owner
- CRevisit the selection and sequencing of backlog items to create a viable integrated plan…
- DAsk the Nexus Integration Team to solve the sequencing problem