When applying WSJF to sequence epics, a portfolio team calculates a Cost of Delay of 8 and a Job Duration of 2. Another epic has a Cost of Delay of 6 and a Job Duration of 1. Which epic should be prioritized?
- AEpic A (CoD=8, Duration=2) because it has the higher Cost of Delay
- BEpic B (CoD=6, Duration=1) because its WSJF score (6) is higher than Epic A's WSJF score…
- CThey are equally important and can be done in any order
- DEpic A should be prioritized because larger epics always deliver more value