What is the primary purpose of post-tensioning in concrete structures?
Post Tensioning Fundamentals
Question · Easy
In an unbonded post-tensioning system, what distinguishes the tendon from a bonded system?
What type of steel strand is most commonly used in unbonded single-strand post-tensioning systems?
Tendon System Components
Trades Exam Prep Podcast
Listen on Spotify
Podcast
What is the primary function of the corrosion-inhibiting coating (grease) applied to unbonded tendons?
What material is typically used for the sheathing (extruded casing) on unbonded single-strand tendons?
If damaged sheathing is discovered on a tendon prior to concrete placement, what is the appropriate repair method?
Question · Medium
What is the function of a stressing-end (live-end) anchor in an unbonded PT system?
What is the function of a dead-end (fixed-end) anchor in an unbonded PT system?
What is the purpose of a pocket former in an unbonded PT system?
What are tendon chairs (support bars or bolsters) used for in unbonded PT installation?
Tendon Layout And Placement
In a typical post-tensioned slab, where is the tendon positioned at midspan between supports?
What is a harped tendon profile?
What is the typical minimum concrete cover required over unbonded tendons in an interior slab per ACI 318?
When placing banded tendons in a post-tensioned slab, how are they typically arranged?
What is the maximum jacking stress typically allowed for 270 ksi strand during stressing?
Stressing Procedures
What is the ultimate breaking strength of a standard 1/2-inch diameter, 270 ksi seven-wire strand?
What minimum concrete compressive strength is generally required before stressing of unbonded tendons can begin?
During the stressing operation, how is the jacking force typically verified?
How often must a hydraulic stressing jack be calibrated per PTI requirements?
What is the purpose of measuring tendon elongation during stressing?
Elongation Calculations
What is the basic formula for calculating theoretical tendon elongation?
A 50-foot unbonded tendon is stressed with a jacking force of 33,000 lbs. If the strand area is 0.153 sq in. and E = 28,500 ksi, what is the approximate theoretical elongation (ignoring friction)?
Question · Hard
What is the typical modulus of elasticity (E) for seven-wire prestressing strand used in elongation calculations?
What happens if the measured field elongation significantly exceeds the calculated theoretical elongation?
What is anchor seating loss (wedge draw-in) in post-tensioning?
What safety precaution must be observed regarding standing position during tendon stressing?
Safety During Stressing
What personal protective equipment (PPE) is required during stressing operations?
What should be done with the tail end of the strand protruding from the anchor after stressing is complete?
Why must flame cutting (torch cutting) NEVER be used to cut post-tensioning strand?
What is the main component of a hydraulic stressing system for single-strand unbonded PT?
Hydraulic Jacks And Pumps
What information must be shown on a jack calibration chart?
What is the typical compressive strength of structural concrete used in post-tensioned buildings?
Basic Concrete Knowledge
What is the purpose of concrete cylinder tests taken during construction of a PT slab?
What precaution must be taken when vibrating concrete around post-tensioning tendons?
Concrete Placement
Why is proper concrete consolidation around anchorage zones especially important?
What is the role of mild reinforcing steel (rebar) in a post-tensioned slab?
Rebar Interaction With Pt
Where is supplemental bonded reinforcement (rebar) typically required in an unbonded PT slab per ACI 318?
What is the primary reference standard published by PTI for field installation and inspection of unbonded single-strand tendons?
Pti Standards
What ACI code governs the design requirements for post-tensioned concrete in buildings?
Aci 318 Pt Basics
According to ACI 318, what is the maximum permissible stress in the prestressing steel immediately after anchor seating?
What document should the installer review before beginning tendon placement on a new project?
Quality Control
What records must be maintained during stressing operations?
Documentation
What is the cross-sectional area of a standard 1/2-inch diameter seven-wire prestressing strand?
What is the function of the two-piece wedge in a stressing-end anchor?
Before concrete placement, what should be verified about the tendon layout?
What is the purpose of intermediate (construction) stressing in multi-pour PT construction?
What must be done to stressing pockets after stressing and tail cutting are complete?
Loading more…