A Kanban team wants to improve their process. Their current cycle time for feature delivery is 12 days. They notice that items often wait in a 'Ready for Development' column for 4 days. According to lean and Kanban thinking, what should the team do first?
- AAdd more developers to reduce the wait time
- BInvestigate and reduce the wait time in the 'Ready for Development' stage as a form of wa…
- CIncrease sprint length to 4 weeks to give more time per feature
- DReplace Kanban with Scrum to improve throughput