Question

A textile plant has an annual insurable gross profit of US$ 1,200,000 and contracts a Business Interruption policy with a sum insured of US$ 1,200,000 for a 12-month indemnity period. A fire shuts down production for 3 months, causing an actual reduction in gross profit of US$ 300,000. To mitigate losses, the company spends US$ 20,000 on renting temporary sewing machinery, which successfully prevented a further US$ 50,000 loss of gross profit. Assuming no underinsurance and a 10-day time deductible valued at US$ 33,333, how are the increased costs of working (gastos extraordinarios para aminorar la pérdida) treated?