An organization's P3O is asked to apply Earned Value Management (EVM) to its strategic programme. The programme is 6 months in. Planned Value (PV) = £500,000, Earned Value (EV) = £420,000, Actual Cost (AC) = £480,000. What does this scenario indicate?
- AThe programme is ahead of schedule and under budget
- BThe programme is behind schedule (EV < PV) and over budget (EV < AC)
- CThe programme is ahead of schedule and over budget
- DThe programme is exactly on track with no variances