Which scheduling practice is best for a project requiring field survey, title research, drafting, review, and client revisions?
- ABuild a sequence with dependencies, review milestones, and float for client or agency res…
- BSchedule every task for the same day
- CSchedule drafting before records are available and never update the plan
- DHide schedule risks until the deadline passes