A masonry firm bids on a facade bricklaying project with expected contract revenue of NOK 1,200,000. Total variable costs (materials, direct labor, equipment rental) are estimated at NOK 840,000. What is the contribution margin (dekningsbidrag - DB) and the contribution ratio (dekningsgrad - DG)?
- ADB = NOK 2,040,000; DG = 58.8%
- BDB = NOK 480,000; DG = 40.0%
- CDB = NOK 360,000; DG = 30.0%
- DDB = NOK 840,000; DG = 70.0%