The contractor submits startup forms with every checkbox marked complete, but no measured voltage, amperage, rotation, or safeties data are included. What should the BSC professional do?
- ARequest the specified measured data or supporting evidence before accepting the forms as…
- BAccept the forms because every box is checked
- CAssume measurements are unnecessary for commissioning
- DMove all missing data to the owner's training agenda