A Mozambican construction firm signs a contract to build a commercial warehouse for 10,000,000 MT over two years, with total estimated contract costs of 7,000,000 MT. In Year 1, costs incurred that reflect progress toward completion are 3,500,000 MT. Using an input (cost-to-cost) method to measure progress under IFRS 15, how much revenue is recognized in Year 1?
- A3,500,000 MT
- B5,000,000 MT
- C7,000,000 MT
- D10,000,000 MT