An automation retrofit project has these activities: A, design (4 weeks); B, procure parts (6 weeks, after A); C, write the PLC program (3 weeks, after A); D, assemble the cell (2 weeks, after B); E, integration and testing (2 weeks, after C and D). Using the critical path method, what is the project duration, and how much total float does activity C have?
- A14 weeks; C has 5 weeks of float
- B17 weeks; C has no float
- C9 weeks; C is on the critical path
- D14 weeks; C has 3 weeks of float