Question

In a man-machine process analysis (diagrama hombre-máquina), an operator manually loads and unloads a semi-automatic lathe in 1.5 minutes. Once started, the lathe runs autonomously for 4.5 minutes. During this automated machining cycle, the operator spends 1.0 minute deburring and gauging the previously completed part, remaining idle for the rest of the time. What is the total cycle time, and what are the operator and machine utilization percentages?