A water treatment plant construction contract has a total Budget at Completion BAC = MUR 50,000,000. At the current progress checkpoint, EV = MUR 20,000,000 and AC = MUR 25,000,000. Assuming future work will proceed at the same cost efficiency experienced to date, what is the Estimate at Completion (EAC)?
- AMUR 45,000,000
- BMUR 55,000,000
- CMUR 62,500,000
- DMUR 75,000,000