According to Earned Value Management (EVM), if a project has an Earned Value (EV) of INR 10,000 and an Actual Cost (AC) of INR 12,000, what is the Cost Variance (CV) and what does it indicate?
- ACV = -INR 2,000; the project is over budget
- BCV = +INR 2,000; the project is under budget
- CCV = -INR 2,000; the project is behind schedule
- DCV = +INR 2,000; the project is ahead of schedule