A Dublin facilities team is planning an office fit-out. The project lead explains why spreadsheet rows alone are insufficient for tracking dependencies between trades. What is the main benefit of dedicated project planning software?
Project Management Concepts
Question · Easy
For a Cork hospital wing refurbishment, the planner must show how deliverables break down from major phases into detailed activities. Which view best represents a work breakdown structure (WBS) inside project software?
A Galway events company stakeholder asks to see tasks plotted as horizontal bars against a calendar timeline. Which chart type should the planner open?
Tech Exam Prep Podcast
Listen on Spotify
Podcast
During planning for a Limerick warehouse upgrade, the sponsor asks which sequence of linked tasks determines the earliest possible project completion. Which concept answers that question?
Question · Medium
Task 'Install signage' in a Waterford retail rollout shows 4 days of total float. What does that mean for the project finish date?
A planner marks 'Planning permission granted' as a zero-duration marker on an Irish housing development schedule. What task type is this?
Tasks
Which diagram displays tasks as boxes connected by arrows to show logical dependencies and help identify the critical path?
An ICDL candidate is asked why organisations adopt project management software instead of wall charts alone. Which answer is most accurate?
In a Cork-to-Dublin rail signage project plan, free float differs from total float. Which statement about free float is correct?
Question · Hard
A trainee planner confuses project phases with individual tasks. Which description best fits a project phase in software terms?
Why might a Kilkenny manufacturing upgrade use both a Gantt chart and a network diagram?
A project manager says a task is 'on the critical path'. Which condition must be true?
A planner opens Project Information for a new Tralee community centre build scheduled forward from a fixed start date. What is the default constraint for new tasks in this mode?
Project Creation
An Irish software launch must hit a fixed release date advertised to customers. Which Project Information setting is most appropriate?
Which project element defines standard working days, default shift hours, and public holiday non-working time for the whole file?
Before sharing a plan with auditors, a planner adds the company name and project manager in file metadata. Where is this information typically stored?
A data-centre cooling test must run continuously including weekends. Which base calendar should be assigned?
A Dublin council project works 8 hours Monday–Thursday and 4 hours Friday. How should the planner configure this pattern?
A planner wants a reusable shell with standard phases for repeated Irish school IT rollouts. What is the correct starting approach?
Why save a completed rollout plan as a template (.mpt or equivalent) for future campuses?
Irish public holidays must be non-working in a national rollout calendar. What is the correct method?
The project start date in Project Information moves from 3 March to 17 March. Tasks with ASAP constraint and no predecessors will:
Default working hours should run 08:30–17:30 for all standard days. Which setting should be changed?
Monthly all-hands meetings block two hours every first Friday. How should the planner reflect this in the calendar?
Concrete must cure for 72 hours continuously including nights and weekends. Which duration entry uses elapsed time?
Selecting 'Indent Task' on a row directly below a phase heading will:
A summary task 'Site preparation' shows 15 days duration. Where does that duration come from?
Which action converts an ordinary task into a milestone in most project tools?
Outdenting a subtask one level will:
A task note contains a hyperlink to the tender document on the council portal. Which feature stores this?
Editing a summary task's start date directly is discouraged because:
A planner enters 40 hours of work on a task with one full-time resource (100% units). If the calendar day is 8 hours, what working duration is expected?
Which field distinguishes effort (work hours) from elapsed calendar time on a task?
Splitting a long task into two sequential subtasks under one summary is primarily used to:
A task duration shows '2.5d?' with a question mark in some tools. What does this typically indicate?
Scheduling And Relationships
Deleting a summary task that contains subtasks will generally:
Which value best represents a milestone duration in the duration column?
A planner renames task IDs after importing a task list. Why must they verify predecessor columns?
For ICDL purposes, entering '1w' as a task duration typically means:
Two tasks: 'Lay flooring' must start only after 'Level subfloor' completes. Which dependency type is the default in most tools?
'Send proofs to printer' should begin 1 day after 'Client sign-off' finishes. How is this entered?
Proofreading may start 2 days before writing finishes. Which link represents that overlap?
The predecessor entry '12SS+3d' on a task means:
The Predecessors column in a task table is used to:
When should Finish-to-Finish (FF) be used?
Task B cannot finish until Task A has started (shift handover pattern). Which relationship applies?
Switching a task from Manually Scheduled to Auto Scheduled will: