Per IBC Section 105.5, after a permit is issued, work must commence within how many days, and once started, may not be suspended for more than how many days, before the permit becomes invalid?
- A90 days / 90 days
- B180 days / 180 days
- C365 days / 180 days
- D12 months / 12 months