Budgeted overhead was £200,000 and budgeted hours 40,000 (rate £5/hour). Actual overhead was £210,000 and actual hours 38,000. Overhead has been:
- AUnder-absorbed by £30,000
- BUnder-absorbed by £20,000
- COver-absorbed by £20,000
- DOver-absorbed by £10,000