During bid review for a commercial office renovation, the installation manager identifies a discrepancy between the specification and the drawings: the spec calls for 28-oz commercial carpet, but the floor plan legend shows 22-oz carpet in several offices. What is the correct response?
- AUse whichever product is cheaper to maximize the bid margin
- BUse the drawing legend because drawings supersede specifications
- CIssue a Request for Information (RFI) to the architect or project owner before submitting…