Two reporting-service designs meet all required reliability constraints. A costs 8,000 units per year with expected annual outage loss of 12,000; B costs 14,000 with expected loss of 3,000. Using only these stated costs and expected losses, which has the lower expected annual total?
- AB, by 3,000 units.
- BA, by 6,000 units.
- CB, by 9,000 units.
- DA, by 9,000 units.