An ICT project consists of five sequential and parallel activities with durations in days: Activity A (Start to Node 1, 4 days), Activity B (Node 1 to Node 2, 6 days), Activity C (Node 1 to Node 3, 3 days), Activity D (Node 2 to Finish, 5 days), Activity E (Node 3 to Finish, 7 days). What is the duration of the Critical Path, and which path constitutes the Critical Path?
- APath A → C → E with duration 14 days
- BPath A → B → D with duration 15 days
- CPath A → B → D with duration 10 days
- DPath B → C → E with duration 16 days