A general contractor and an owner agree on a fixed lump-sum price (Pauschalpreis) of CHF 2,500,000 for the construction of a commercial building. During construction, the contractor incurs CHF 300,000 in additional labor and material costs due to general inflation and supply chain price spikes. Can the contractor demand a price increase under Art. 373 OR?
- ANo, because under Art. 373 Abs. 1 OR, a lump-sum price is strictly binding, and general m…
- BYes, because under Art. 373 Abs. 2 OR, any cost increase exceeding 10% automatically enti…
- CYes, because under Art. 374 OR, whenever contractor expenses increase, the lump sum is co…
- DNo, but the contractor may unilaterally cancel the contract without paying damages under…