Question

A painting enterprise in the Canton of Zurich employs 12 journeymen painters under the Swiss Collective Employment Agreement for the Painting and Plastering Trade (GAV Maler- und Gipsergewerbe). During the busy summer season, several employees work 45 hours per week. How does the GAV annual working time model (Jahresarbeitszeitmodell) regulate weekly maximum working hours and the compensation of overtime (Überstunden)?

Unternehmensfuehrung Und Recht

Question · Medium

Question

A painting contractor completes interior painting works for a commercial office building under a contract incorporating SIA-Norm 118. Fourteen months after the formal joint acceptance inspection (Gemeinsame Abnahmeprüfung), the client discovers hairline shrinkage cracks along several drywall corner joints and immediately notifies the contractor. How does SIA-Norm 118 regulate the defect notification period (Rügefrist) compared to statutory Swiss Code of Obligations (OR Art. 367)?

Unternehmensfuehrung Und Recht

Question · Easy

Question

A master painting contractor executes a facade coating project under a fixed lump-sum contract (Pauschalvertrag nach OR Art. 373). During the works, extreme unseasonal torrential rainfall exceeding 100-year historical records causes severe structural groundwater flooding and substrate saturation, preventing coating application for six weeks and causing substantial extra heating and dehumidification costs. Can the contractor claim price adjustments under OR Art. 373 Abs. 2?

Unternehmensfuehrung Und Recht

Question · Medium

Question

A newly qualified Malermeister takes over an established 15-person painting firm and conducts a strategic SWOT analysis. The firm possesses deep expertise in mineral lime techniques and historic monument restoration but faces intense price competition in new residential drywall painting. Which strategic positioning represents the most sustainable competitive differentiation?

Unternehmensfuehrung Und Recht

Question · Easy

Question

During the formal joint acceptance inspection (Gemeinsame Abnahmeprüfung nach SIA 118 Art. 158) of exterior facade painting on an apartment complex, the architect and the master painter identify minor touch-up requirements along three window reveals. What legal effect does signing the joint acceptance protocol (Abnahmeprotokoll) have regarding the transfer of risk and the guarantee period?

Unternehmensfuehrung Und Recht

Question · Medium

Question

A master painter reviews the annual balance sheet of their enterprise. The financial data indicates: Cash & Bank balances = CHF 120,000; Trade receivables (Forderungen aus L&L) = CHF 180,000; Inventories (Vorräte/Material) = CHF 80,000; Short-term liabilities (Kurzfristiges Fremdkapital) = CHF 250,000. What is the enterprise's Quick Ratio (Liquiditätsgrad 2), and does it meet standard Swiss financial benchmarks?

Unternehmensfuehrung Und Recht

Question · Hard

Question

In a unit price contract (Einheitspreisvertrag) governed by SIA-Norm 118, the tendered quantity for exterior facade washing and biocide treatment was estimated at 1,000 m² at CHF 18.00/m². Due to substantial architectural additions requested by the owner, the actual executed quantity reaches 1,350 m² (+35%). How does SIA-Norm 118 Art. 86 regulate unit price adjustments when quantities vary significantly?

Unternehmensfuehrung Und Recht

Question · Hard

Question

While cleaning facade spray equipment on a construction site near a lake in Lucerne, an apprentice inadvertently spills 40 liters of solvent-thinned 2K epoxy primer into an open storm drain (Meteowasserkanal) that discharges directly into the lake. What immediate legal liabilities and regulatory notifications arise under the Swiss Water Protection Act (Gewässerschutzgesetz GSchG)?

Unternehmensfuehrung Und Recht

Question · Medium

Question

A painting master is contracted to apply a high-grade polyurethane floor coating in a new commercial warehouse. On site, the master measures the concrete floor moisture at 6.2 CM-% (excessive) and observes severe laitance (Sinterschicht). The client insists in writing on immediate coating application to meet an immovable tenant opening date. What is the master's legal duty under OR Art. 365 Abs. 3 and SIA 118 Art. 25?

Unternehmensfuehrung Und Recht

Question · Hard

Question

A post-calculation (Nachkalkulation) on a completed 24-apartment refurbishment project shows: Tendered target labor (Soll-Stunden) = 1,200 hours at CHF 80.00/h (CHF 96,000); Effective executed labor (Ist-Stunden) = 1,480 hours at CHF 80.00/h (CHF 118,400); Material costs matched budget exactly at CHF 28,000. What is the labor variance in hours and percent, and what action should the Malermeister take?

Projektleitung Und Kalkulation

Question · Medium

Question

A paint wholesaler's invoice offers the following payment terms: '2% Skonto within 10 days, or net 30 days'. The master painter evaluates whether to draw on the company's bank overdraft facility (Kontokorrentkredit at 7.5% annual interest) to pay on Day 10. What is the approximate annualized interest rate represented by the early payment discount (Skonto), and is it financially advantageous to take it?

Projektleitung Und Kalkulation

Question · Easy

Question

At the conclusion of a commercial office fit-out, the general contractor deducts CHF 3,500 from the painting company's final payment, claiming a lump-sum back-charge (Gegenrechnung) for 'general site cleanup and waste disposal'. The painting company had cleanly cleared all its own masking, paint cans, and debris daily and maintained photo logs. How should the Malermeister contest this unauthorized back-charge under SIA-Norm 118?

Projektleitung Und Kalkulation

Question · Easy