Question

A Swiss general contractor and an electrical installation company incorporate SIA Standard 118 into their construction contract. Fourteen months after formal acceptance (Werkabnahme), the building owner discovers an intermittent neutral connection in a sub-distribution panel. How does SIA Standard 118 Art. 172/173 govern the owner's defect notification rights (Rügefrist) compared to the statutory Swiss Code of Obligations (OR Art. 367)?

Unternehmensfuehrung Und Recht

Question · Easy

Question

An electrical contractor signs a fixed lump-sum contract (Pauschalpreisvertrag under OR Art. 373) to wire a new office building for CHF 120,000. During execution, material prices for copper cables increase by 15%, and unforeseen ground water in the basement requires additional conduit routing not shown in the original architectural plans. Can the contractor claim extra compensation?

Unternehmensfuehrung Und Recht

Question · Medium

Question

An electrical contractor's commercial liability insurance (Betriebshaftpflichtversicherung) policy covers third-party bodily injury and property damage. While installing a sub-panel, an apprentice accidentally drops a heavy tool onto the client's marble flooring, cracking two tiles (CHF 3,500 damage). In the same incident, the apprentice incorrectly wires a control relay inside the panel, burning out the relay (CHF 600 component cost). How does the insurer handle these claims?

Unternehmensfuehrung Und Recht

Question · Medium

Question

Under NIN 5.6 (Sicherheitsstromversorgung) and VKF guidelines, an emergency power supply system is designed for an acute care hospital. Operating theater life-support systems require an uninterrupted power supply (UPS / USV) with a changeover time of ≤ 0.5 s (Class 0.5), while emergency smoke extraction fans require power within 15 s (Class 15). How must the electrical architecture be configured?

Projektierung Und Engineering

Question · Medium