Question

A Swiss construction AG has a fully paid-in share capital (Aktienkapital) of CHF 2,000,000 and statutory legal reserves (gesetzliche Gewinn- und Kapitalreserven) of CHF 600,000. At the financial year-end closing, the audited balance sheet shows accumulated operating losses of CHF 1,400,000, reducing reported net equity (Eigenkapital) to CHF 1,200,000. Under revised Swiss corporate law (Art. 725a OR), what is the legal status and mandatory obligation of the Board of Directors?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Medium

Question

A Baumeister enterprise owns a fleet of crawler excavators and heavy dump trucks with a historical acquisition cost of CHF 6,000,000 and an estimated fair market value of CHF 3,200,000. In the statutory commercial balance sheet under Art. 960a OR, the fleet has been depreciated down to a symbolic book value of CHF 1. What are the legal implications regarding hidden reserves (stille Reserven) under Art. 959c and 960e OR?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Medium

Question

A mid-sized Swiss construction enterprise operates two primary profit centers: Structural Building (Hochbau) and Civil Infrastructure (Tiefbau). Hochbau generates revenue of CHF 18,000,000 with direct project costs (Einzelkosten) of CHF 13,500,000 and dedicated division overhead (Spartengemeinkosten) of CHF 1,500,000. Tiefbau generates revenue of CHF 12,000,000 with direct project costs of CHF 8,000,000 and dedicated division overhead of CHF 1,200,000. Central corporate overhead (Unternehmensgemeinkosten) is CHF 3,000,000. What is the Contribution Margin II (Deckungsbeitrag II) of Hochbau and Tiefbau respectively, and what is the overall net corporate operating profit (Betriebsergebnis)?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Medium

Question

During severe winter weather in January, an excavation and concrete contractor cannot proceed with earthworks in Graubünden for 8 consecutive working days due to deep frost and snow. The contractor claims bad weather compensation (Schlechtwetterentschädigung / SWE) under the Swiss Unemployment Insurance Act (AVIG Art. 42 ff.). What is the mandatory procedure and benefit level?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Medium

Question

A Swiss Baumeister company shows the following balance sheet figures at year-end: Total Assets = CHF 25,000,000; Fixed Assets (Anlagevermögen: plant, machinery, real estate) = CHF 12,000,000; Current Assets = CHF 13,000,000; Equity (Eigenkapital) = CHF 8,000,000; Long-term Debt (langfristiges Fremdkapital) = CHF 7,000,000; Short-term Debt = CHF 10,000,000. What is the Asset Coverage Ratio II (Anlagendeckungsgrad II / Golden Balance Sheet Rule), and does it fulfill standard financial benchmarks?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Medium

Question

A retiring Baumeister plans to sell his operational construction enterprise to his two senior project managers. They are deciding between a Share Deal (sale of 100% of AG shares) and an Asset Deal (transfer of operational assets and contracts under the Swiss Merger Act / Fusionsgesetz FusG Art. 69 ff.). What is a decisive legal and labor consequence regarding existing employment contracts under Art. 333 OR?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Medium

Question

A regional Baumeister enterprise faces severe liquidity distress following heavy losses on a major infrastructure project. The balance sheet shows negative equity of CHF 1,800,000 (Überschuldung under Art. 725b OR). To prevent immediate notification of the bankruptcy judge, the principal shareholder agrees to subordinate a shareholder loan (Aktionärsdarlehen) of CHF 2,000,000. What statutory requirements must this subordination (Rangrücktritt) satisfy under Swiss law?

Strategische Und Finanzielle Unternehmensfuehrung

Question · Hard

Question

During the execution of a concrete superstructure under a unit-price contract governed by SIA 118, the client's site supervisor (Bauleitung) orders an additional intermediate reinforced concrete wall not included in the original project plans. According to SIA 118 Art. 84-91, what is the mandatory requirement for the contractor (Baumeister) regarding additional compensation claims (Mehrvergütungsansprüche)?

Baurecht Und Vertragswesen

Question · Medium