A mid-sized Swiss construction enterprise operates two primary profit centers: Structural Building (Hochbau) and Civil Infrastructure (Tiefbau). Hochbau generates revenue of CHF 18,000,000 with direct project costs (Einzelkosten) of CHF 13,500,000 and dedicated division overhead (Spartengemeinkosten) of CHF 1,500,000. Tiefbau generates revenue of CHF 12,000,000 with direct project costs of CHF 8,000,000 and dedicated division overhead of CHF 1,200,000. Central corporate overhead (Unternehmensgemeinkosten) is CHF 3,000,000. What is the Contribution Margin II (Deckungsbeitrag II) of Hochbau and Tiefbau respectively, and what is the overall net corporate operating profit (Betriebsergebnis)?
- AHochbau DB II = CHF 4,500,000; Tiefbau DB II = CHF 4,000,000; Operating Profit = CHF 5,50…
- BHochbau DB II = CHF 3,000,000; Tiefbau DB II = CHF 2,800,000; Operating Profit = CHF 2,80…
- CHochbau DB II = CHF 1,500,000; Tiefbau DB II = CHF 1,600,000; Operating Profit = CHF 100,…
- DHochbau DB II = CHF 3,000,000; Tiefbau DB II = CHF 4,000,000; Operating Profit = CHF 4,00…