Which thesis scope is most suitable for demonstrating independent Tiefbau construction-management competence?
Diplomarbeit Praesentation Fachgespraech
Question · Easy
A thesis investigates whether groundwater caused excavation delay. Which evidence combination is strongest?
Question · Medium
A thesis compares open-cut and trenchless installation beneath a busy road. Which evaluation produces the most defensible recommendation?
Question · Hard
Engineering Exam Prep Podcast
Listen on Spotify
Podcast
A thesis contains monitoring data exported from the client's system and calculations prepared by the candidate. How should this be presented?
What should a candidate prioritize in the official 15-minute thesis presentation?
In the 45-minute thesis interview, the examiner asks how the recommendation changes if the assumed groundwater inflow doubles. What response shows the strongest competence?
Before mechanical excavation starts in a corridor containing existing utilities, what is the strongest control?
Projektleitung Recht Sicherheit
A rectangular trench is 75 m long, 1.20 m wide and 2.00 m deep. Ignoring overbreak, services and bulking, what in-situ excavation volume is represented?
A traffic stage must change one night earlier than the approved plan. What should the Bauleiter establish before authorizing the switch?
Monitoring shows turbid construction water approaching the project's authorized discharge limit. What should the Bauleiter do?
An excavator damages a suspected gas service. What is the immediate priority?
A municipality, utility owner and contractor issue conflicting requirements for a road-opening sequence. What should the Bauleiter do?
A unit-price road-subbase item has an agreed rate of CHF 48.00/m³. The verified quantity under the contract measurement rules is 3,820 m³. What is the gross item amount before any other contractual adjustment?
Finanzielle Fuehrung Qualitaet
During a public-tender check, the stated unit rate multiplied by the stated quantity does not equal the bidder's item total. What should the evaluator do?
An approved change replaces disposal already priced at CHF 18.00/m³ with a route costing CHF 65.00/m³ for 1,200 m³. If the change valuation is defined as the incremental disposal cost only, what amount follows?
A contract formula states that a CHF 220-per-tonne increase in bitumen price is applied to asphalt containing a 5.5% bitumen mass fraction. What is the raw material adjustment per tonne of asphalt?
A public-works bid is substantially below the other tenders and the estimate. What is the sound evaluation response?
Which cost-control entry best represents a pending utility-relocation change?
Before backfilling a retaining wall, which verification is most important?
Konstruktion Tiefbau
A deep excavation has an upward groundwater gradient beneath its base. Which evidence is needed before relying on dewatering alone to prevent hydraulic heave?
An excavation-support inclinometer reaches the project's amber trigger and its rate of movement is increasing. What is the best response?
What does a laboratory Proctor test provide for earthwork quality control?
A road project will increase runoff to a receiving system. What should the Bauleiter verify before connecting the permanent drainage?
Before accepting installed bridge bearings, which record set is most important?