In Material Requirements Planning (MRP I), a production planner calculates net requirements for component X in week 36. Gross requirements are 1,000 units, current physical stock is 300 units, allocated stock for other orders is 100 units, scheduled incoming receipts are 200 units, and safety stock is 100 units. What is the net requirement (Nettobedarf)?
- A700 units
- B600 units
- C500 units
- D800 units