Question

A subcontractor is behind schedule on a fixed-price job. The main contractor, who will face a penalty from the owner if the project is late, promises the subcontractor extra payment per unit to ensure timely completion, and the subcontractor finishes on time. The main contractor obtains a practical benefit (avoiding the penalty and the cost of finding a replacement) and there is no economic duress. Under the approach in Williams v Roffey Bros, which Canadian courts have considered, is the extra promise enforceable?

Consideration

Question · Hard