A contractor is analyzing a project's financial status at year-end. Total contract value is $5,000,000. Total estimated costs at completion are $4,500,000. Cumulative costs incurred to date are $1,800,000. Cumulative billings to date are $2,200,000. Using the percentage-of-completion method, what is the Earned Revenue to date?
- A$2,000,000
- B$1,800,000
- C$2,200,000
- D$2,500,000