A renewable energy project requires an initial capital investment (Year 0) of R$ 1,000,000. It produces net operational cash inflows of R$ 440,000 at Year 1, R$ 484,000 at Year 2, and R$ 399,300 at Year 3. At a project discount rate (WACC) of 10.0% per annum, what is the exact Net Present Value (NPV / VPL) of the project?
- A-R$ 50,000.00
- BR$ 0.00
- CR$ 323,300.00
- DR$ 100,000.00