BuildCorp enters into a contract on 1 January 2024 to construct a commercial warehouse for a client for a fixed fee of Tk. 10,000,000. The contract specifies a completion date of 31 December 2024. If completed on time, BuildCorp receives a bonus of Tk. 2,000,000. Due to potential severe monsoon rains, BuildCorp estimates a 70% probability of completing on time (receiving Tk. 12,000,000 total) and a 30% probability of a one-month delay (receiving only Tk. 10,000,000). Management concludes it is NOT highly probable that a significant reversal will not occur regarding the bonus. At 31 December 2024, the project is 60% complete based on costs incurred. What is cumulative revenue recognized at 31 December 2024 under IFRS 15?
- ATk. 6,000,000
- BTk. 7,200,000
- CTk. 6,840,000
- DTk. 10,000,000