A construction checklist for a pump shows blank fields for rotation, vibration observation, strainers, valve position, and startup report. The contractor asks to proceed directly to FPT. What is the best response?
- ARequire completion or resolution of readiness items before functional testing the pump sy…
- BProceed because checklists are unrelated to pump operation
- CMark all blanks as passed to preserve the schedule
- DCancel all pump commissioning activities