Under Australian WHS regulations, which document must be prepared before high-risk construction work such as basic rigging?
Planning Rigging Work
Question · Easy
What is the typical prerequisite High Risk Work Licence class before enrolling in Basic Rigging (RB / CPCCLRG3001)?
In the SafeWork NSW hierarchy of dogging and rigging licences, which statement is correct for a Basic Rigging (RB) holder?
Which of the following is WITHIN Basic Rigging (RB) licence scope under SafeWork NSW?
Under the WHS Act, what is a worker’s primary duty of care while performing basic rigging?
What is the first (most effective) step in the hierarchy of hazard control when planning a lift?
How long is an Australian High Risk Work Licence typically valid before renewal is required?
After a satisfactory NAI assessment for RB, within what period must you typically apply to the state WHS regulator for the licence?
Which communication method is commonly used between a rigger/dogman and crane operator when radios fail?
Before starting basic rigging, what must you do regarding site-specific hazards?
A rigger is about to work near overhead powerlines. What planning action is required?
Question · Medium
Why should a basic rigger not walk or work on structural steel that is wet from rain or fresh paint without additional controls?
Where should you find manufacturer requirements for inspection, use, maintenance and storage of rigging gear?
Which fall-related control is typically preferred as a higher-order control when working at height during steel erection?
Who is responsible for ensuring ground/foundation suitability is assessed before placing heavy plant or structures during basic rigging setup?
A 2.4 t load will be lifted with a two-leg wire-rope sling. Each leg is at 60° to the horizontal (30° from vertical). Approximate tension in each leg (idealised, equal share)? Use T = (W/2) / cos(θ) with θ = 30° from vertical (cos 30° ≈ 0.866).
Question · Hard
A 3.0 tonne load is supported on a single vertical sling. What is the tension in that sling (neglecting sling self-weight)?
A load of 4.0 t is lifted on two vertical legs of equal length sharing equally. What tension is in each leg?
If sling angle to the horizontal decreases (legs become flatter) while supporting the same load on a two-leg bridle, what happens to sling tension?
A basic rigger must calculate loads associated with mechanical load-shifting equipment. Which statement is correct?
Which weather condition should typically stop outdoor steel erection and lifting until controls are reviewed?
What is the purpose of exclusion zones and barricades during basic rigging?
National Assessment Instruments (NAI) for HRW classes such as RB typically include which assessment components?
A trainee may perform high risk rigging work without holding the licence only when:
A 5.0 t load is lifted on a two-leg bridle with each leg at 45° to the horizontal. Using the approximate factor that each leg tension ≈ 0.71 × W for equal 45° legs to horizontal (or T = (W/2)/sin(45°) with sin45°≈0.707), what is each leg tension?
What action must you take if a synthetic sling has a deep cut or serious abrasion at pre-use inspection?
Select Inspect Equipment
Under AS 4497 colour coding for synthetic roundslings, which colour typically indicates a 2 tonne WLL?
If a lifting chain’s WLL tag is missing or illegible, what should you do?
What does WLL stand for on lifting gear?
Before use, communication equipment for directing a lift must be:
A Grade 80 chain sling is marked WLL 3.15 t in a single-leg vertical configuration. For a choker hitch, manufacturers often apply a reduction factor (commonly about 0.8). Approximate allowable load in choker?
Wire rope shows several broken wires in one strand and birdcaging. What is the correct action?
Shackles used for lifting should be selected so that:
Personal protective equipment (PPE) for basic rigging typically includes:
A fibre roundsling is exposed to welding spatter and shows melted fibres. What should you do?
When selecting a sling for a sharp-edged steel beam, what protection is required?
A chain block is to lift 1.8 t. The block is marked WLL 2.0 t. Is it suitable (static, vertical, within duty)?
An ideal moving single-sheave block (gun tackle / moving snatch block) gives about 2:1 mechanical advantage (ignoring friction). If the effort (line pull) is 0.5 t, what approximate load can be raised?
Pre-use inspection of a lever hoist (tirfor/come-along style or lever chain hoist) should include checking:
A two-leg sling has a manufacturer rating chart showing WLL 4.0 t at 60° included angle and 2.8 t at 90° included angle for the assembly. For a lift requiring 3.2 t at 90° included, what should you do?
Taglines are primarily used to:
Synthetic sling colour fades and the label is still readable showing WLL 3 t (yellow). Capacity for selection is based on:
A 2.0 t load is choked with a single sling. Manufacturer states choker WLL = 0.8 × vertical WLL. Minimum vertical WLL required for the sling?
Eyebolts for lifting should be:
After dismantling, defective plant/gear must be:
Basic Rigging (RB) includes which steel-related activity?
Structural Steel And Plant
When erecting a steel portal frame, stability must be maintained by:
Purlins and girts should typically be installed: