Which code chapter of the International Building Code (IBC) governs special inspections and tests for post-installed anchors in concrete on commercial projects?
Ibc Chapter 17 Special Inspections
Question · Easy
Per ACI 318-19, Chapter 17 governs the design and qualification of anchors. What does ACI 318 Chapter 17 primarily address?
Aci 318 Chapter 17
Which ACI standard provides qualification testing requirements for post-installed mechanical anchors in concrete?
Anchor Qualification Standards
Trades Exam Prep Podcast
Listen on Spotify
Podcast
Which ACI standard provides qualification testing requirements for post-installed adhesive anchors in concrete?
A wedge anchor, such as a Kwik Bolt or Power-Stud, is classified as which type of post-installed anchor?
Mechanical Anchor Types
A drop-in anchor is classified under ACI 318 Chapter 17 as which of the following?
Question · Medium
A concrete screw anchor (e.g., Titen HD, Tapcon+) transfers load primarily by what mechanism?
Which of the following is the best example of a true undercut anchor?
Adhesive anchors are classified by the chemistry of the bonding agent. Which of the following is NOT a common adhesive anchor chemistry?
Adhesive Anchor Types
Per ACI 318-19 Section 17.1.2, an adhesive anchor qualified under ACI 355.4 and installed horizontally or upwardly inclined to resist SUSTAINED tension loads must be installed by:
What is the primary role of the special inspector on a post-installed anchor installation?
Inspector Role Responsibilities
According to IBC Table 1705.3, inspection of the installation of post-installed mechanical anchors resisting tension or shear loads in concrete is typically classified as:
Inspection of adhesive anchors installed in HORIZONTAL or UPWARDLY INCLINED orientations to resist sustained tension loads is required to be:
Manufacturer's Printed Installation Instructions (MPII) for post-installed anchors must be:
Product Verification
The product approval document most commonly referenced for post-installed anchors in the United States is:
Before any anchor is installed, the inspector should verify that the product on site matches the approved submittal. Which of the following is an acceptable alternative to an ICC-ES ESR?
ICC-ES AC193 is the acceptance criteria used for which of the following?
Question · Hard
ICC-ES AC308 is the acceptance criteria used for which of the following?
The most common drilling method approved for post-installed anchors in concrete is:
Hole Drilling
When a contractor uses a diamond-core-drilled hole for an adhesive anchor, the inspector must verify that:
When verifying the drilled-hole DIAMETER, the inspector should primarily check against:
For a torque-controlled wedge anchor, the drilled hole depth should be:
For ADHESIVE anchors, the drilled hole depth must be:
Hole cleaning is MOST critical for which type of post-installed anchor?
Hole Cleaning
A typical hole-cleaning sequence for an adhesive anchor per MPII is:
Compressed air used to clean holes for adhesive anchors must be:
Which brush type is appropriate for cleaning an adhesive anchor hole?
A worn wire brush that is undersized (too small for the hole) should be:
For an adhesive anchor MPII that specifies a '2-2-2' cleaning sequence, a hole that is twice the depth of the reference depth generally requires:
Torque-controlled wedge anchors are set by applying a specified INSTALLATION TORQUE. The purpose of this torque is to:
Mechanical Anchor Installation
Installation torque for a wedge anchor should be applied with:
A wedge anchor is torqued BELOW the MPII specified installation torque. What is the most likely consequence?
A wedge anchor is torqued ABOVE the MPII maximum installation torque. What is the most likely consequence?
For a drop-in anchor, the inspector verifies that the setting tool has been driven until:
A setting tool for a drop-in anchor must be:
Screw anchors (concrete screws) are typically installed with:
Adhesive anchor installation begins with hole drilling and cleaning. The next step is:
Adhesive Anchor Installation
After the adhesive is injected and the anchor is inserted, the inspector should expect to see:
Per MPII, the inspector should NOT disturb a newly installed adhesive anchor until:
Adhesive working (gel) time is strongly affected by:
Below a minimum concrete temperature specified in the MPII, adhesive anchors:
Before injecting adhesive from a two-part cartridge, the installer must:
A static mixing nozzle on an adhesive cartridge should be:
When an adhesive anchor is inserted into a filled hole, it should be:
ACI 318-19 requires post-installed anchors used in the TENSION zone of concrete structures to be qualified for:
In ACI 318-19, embedment depth of a post-installed anchor is denoted by the symbol:
Edge distance in ACI 318-19 anchor design is symbolized c_a1 for the direction of shear and affects which failure mode the most?