A Florida Certified Solar Contractor is preparing for the state trade knowledge examination. Which three content areas make up the published exam outline, and what are their weights?
Exam Overview
Question · Easy
OSHA fall heights, to scale
Short
The CILB Solar Trade Knowledge exam contains 80 scored questions to be completed in 5 hours with a passing score of 70%. How many questions must a candidate answer correctly to pass?
Exam Logistics
Under the Florida Building Code and NEC, which reference governs the installation of rooftop photovoltaic source and output circuits on a dwelling?
Code References
Trades Exam Prep Podcast
Listen on Spotify
Podcast
Which NEC article addresses the interconnection of a PV inverter output to a utility-interactive electrical power production source?
A PV module has a rated short-circuit current (Isc) of 9.5 A. Per NEC 690.8, what current must be used to size the PV source-circuit conductors for continuous operation?
Pv Circuit Sizing
Question · Medium
Using NEC 690.8, a PV source circuit conductor must carry an Isc of 9.5 A. What minimum conductor ampacity is required before any condition-of-use derating, applying both the 690.8(A) and 690.8(B) factors?
A rooftop PV system in Florida has a maximum DC voltage of 385 V from a series string. Which NEC requirement is triggered because the system is mounted on a building and exceeds 80 V?
Pv Safety
Per NEC 690.12 in the 2020 edition, rapid shutdown of a building-mounted PV system must limit controlled conductors outside the array boundary to what voltage within 30 seconds?
Rapid Shutdown
Question · Hard
A 10 kW PV array in central Florida produces energy at an average of 5.5 peak sun hours per day with a system efficiency (performance ratio) of 0.80. What is the estimated daily energy output?
Pv Energy Production
A residence uses 32 kWh per day. Using 5.5 peak sun hours and a 0.80 performance ratio, what minimum PV array size (DC kW) is needed to offset 100% of the load?
Pv System Sizing
A PV module has a rated open-circuit voltage (Voc) of 39.5 V at Standard Test Conditions. The cold-temperature voltage correction factor for the lowest expected ambient in the installation area is 1.10. What is the maximum source-circuit voltage for a string of 12 modules in series?
Pv String Voltage
An inverter has a maximum DC input voltage of 600 V. Using modules with STC Voc of 39.5 V and a cold-temperature correction factor of 1.10, what is the maximum number of modules that can be wired in series without exceeding the inverter limit?
Pv String Sizing
A PV source circuit carries 8 A through 100 ft (one-way) of #10 AWG copper conductor with a resistance of 1.24 ohms per 1000 ft. Using the NEC voltage-drop formula for single-phase DC, what is the voltage drop on a 48 V nominal circuit?
Voltage Drop
What is the percent voltage drop in the previous 48 V DC circuit with a 1.984 V drop?
A utility-interactive PV system is to backfeed a 200 A residential load center that has a 200 A main breaker. Per NEC 705.12(B)(3) in the 2020 edition, what is the maximum rated PV backfeed breaker allowed on the busbar using the 120% allowance?
Interconnection
If the same 200 A load center has its main breaker derated to 175 A, what is the new maximum PV backfeed breaker allowed by the 120% rule?
Which conductor type is permitted by NEC 690.31(C) for exposed single-conductor PV array wiring between modules on a rooftop?
Pv Wiring
What is the primary function of a grid-interactive (utility-interactive) PV inverter?
Inverters
What anti-islanding requirement must a utility-interactive PV inverter meet under IEEE 1547 and NEC 705?
A 12-module PV string uses modules rated at 39.5 V Vmp and 8.0 A Imp each. What is the string's rated maximum power operating voltage and current?
Pv Series Parallel
What is the rated maximum power (Pmp) of the 12-module string in the previous question at STC?
Pv Power
Per NEC 690.43 and 690.46, what is the purpose of bonding the metallic frames of PV modules to the equipment grounding conductor?
Grounding Bonding
In the 2020 NEC, which section requires ground-fault detection and interruption for the DC circuits of a PV system mounted on a building?
A PV system includes a DC disconnect between the array and the inverter. Per NEC 690.17, what rating must this disconnect have if it is intended to be opened under load?
Disconnects
When sizing an overcurrent device for a PV source circuit with a maximum current of 11.875 A per NEC 690.8, and using the next-size-up rule, what is the minimum standard fuse or breaker size (NEC 240.6 standard sizes: 15, 20, 25, 30)?
Overcurrent Protection
Per NEC 690.53 in the 2020 edition, what information must appear on the permanent label at a PV DC disconnecting means?
Labeling
On a Florida PV installation, the module temperature coefficient for Voc is -0.32%/C and the lowest expected ambient is 5 C. The STC Voc is 39.5 V and STC cell temperature is 25 C. What is the approximate cold-corrected Voc?
Pv Temperature Effects
Why are PV modules typically derated in field conditions compared to their STC rating?
Which OSHA 29 CFR 1926 fall protection requirement applies to PV installers working on a roof with a 12-foot eave height?
Osha Safety
Per OSHA 29 CFR 1926, which PPE is required for a PV installer working on an energized DC string during commissioning?
A PV array produces 6,000 W under full sun. The inverter has a CEC weighted efficiency of 96%. What is the AC output power?
Which type of PV module is best suited for a hot Florida rooftop where partial shading from a nearby tree affects part of the array in the afternoon?
Pv System Design
When commissioning a grid-interactive PV system, which test verifies that the inverter anti-islanding function works correctly?
Commissioning
When mounting a rooftop PV array in Florida, which building-code consideration governs the structural attachment of the racking to the roof trusses?
Mounting Structural
Per NEC 690.31, where PV DC conductors are run in a conduit through a building before reaching the inverter, what additional marking is required at the conduit?
A standalone PV system must power a continuous 200 W load for 3 days of autonomy on a 48 V battery bank. Assuming a 90% battery round-trip efficiency and a maximum 80% depth of discharge, what minimum battery capacity (Ah) is required?
Battery Sizing
What is the recommended tilt angle for a fixed south-facing PV array in central Florida (latitude about 28 degrees N) to maximize annual energy production?
What unit is used to express peak solar irradiance at Standard Test Conditions for PV module rating?
Solar Resource
Under Florida's net-metering rule (PSC Rule 25-6.065), how is excess PV energy exported to the utility typically compensated for a residential customer under 100 kW?
Net Metering
Three PV source circuits are paralleled in a combiner box. Under what condition does NEC Article 690 require each source circuit to carry its own overcurrent protective device?
A 9 kW DC PV array is paired with a 7.5 kW AC inverter. What is the DC-to-AC (inverter loading) ratio, and is it typical for a Florida residential system?
A PV module is rated at 400 W STC. Real-world operating conditions produce a 0.85 derate factor (temperature, soiling, inverter, wiring). What is the expected AC output of one module under those conditions?
Which NEC article section addresses the marking and warning labels required at the AC point of connection for a utility-interactive PV system?
What is the primary purpose of a battery-based PV charge controller in an off-grid system?
Charge Controllers
Using Walker's Building Estimator's Reference Book, which cost category should be added to direct labor and material when estimating a PV installation bid price?
Estimating
On a PV plan set, what does the single-line diagram show?
Plan Reading