An estimator calculates a job requiring 40 total crew hours. If the direct labor rate is $30/hr, labor burden is 40%, and overhead is 20%, what is the break-even labor cost?
- A$1,680 total labor cost.
- B$1,200 total labor cost.
- C$2,400 total labor cost.
- D$2,016 total labor cost.