Under FAA Item P-152, what is the primary purpose of proof-rolling a prepared subgrade before placing base or pavement?
Sitework
Question · Easy
When compacting embankment under typical FAA P-152 earthwork requirements, moisture content is controlled primarily to:
Clearing and grubbing for an airport project typically requires removal of which materials within the work limits?
Trades Exam Prep Podcast
Listen on Spotify
Podcast
Unsuitable material discovered in the runway subgrade should generally be:
Blue tops on an airport grading job are primarily used to:
Under OSHA excavation rules commonly applied on sitework, spoil piles and equipment generally must be kept at least how far from the edge of an excavation?
A trench 4 feet deep on the airfield requires a safe means of egress so that no worker travels more than how far laterally to reach it?
For airport embankments, material is typically placed in lifts primarily to:
What is the main function of an underdrain system installed under or beside airfield pavement?
Silt fence on an airport sitework project is primarily intended to:
Borrow material for runway embankment must generally be:
Question · Medium
Maximum dry density and optimum moisture for embankment acceptance testing are most commonly established by:
A nuclear density gauge on compacted subgrade is used primarily to measure:
When finishing the graded runway safety area (RSA) surface, the contractor should ensure grades:
Topsoil stripped from the site before mass grading is usually stockpiled so it can later be used for:
If embankment material is too wet to achieve specified density, the preferred first corrective action is usually to:
A culvert installed under an airfield haul road or graded area must primarily provide:
Before placing granular subbase (FAA Item P-154 class work), the prepared subgrade should be:
When hauling borrow across existing airfield pavement that must remain in service, the contractor should primarily:
Frost heave risk under airfield pavements is reduced primarily by:
A shrinkage factor of 15% means that to obtain 10,000 compacted cubic yards of embankment, approximately how many bank cubic yards must be excavated?
Question · Hard
Cross-slope on finished airfield graded surfaces is provided mainly to:
When utility conflicts are found during runway sitework excavation, the contractor should:
Filter fabric (geotextile) under a drainage aggregate trench is typically used to:
Which condition most clearly indicates a prepared subgrade is not ready for base placement?
Dust control on open airport earthwork is important because dust can:
Select fill placed in a utility trench under future runway pavement should be compacted:
A temporary diversion ditch during runway reconstruction is mainly intended to:
If a nuclear density test fails on an embankment lift, the contractor should typically:
Finished turf establishment in graded airfield areas generally requires which sequence?
A stockpile of select base aggregate should be managed to prevent:
Why is dewatering often required during deep excavation for drainage structures on airfield projects?
When balancing cut and fill on a runway reconstruction, the earthwork plan should primarily account for:
FAA Item P-401 generally covers construction of which airfield pavement type?
Runway Pavement
FAA Item P-501 is the standard specification for:
A principal structural difference between flexible and rigid airfield pavements is that:
Crushed aggregate base under airfield pavement must be placed and compacted primarily to:
Asphalt mix temperature is critical at placement because:
Percent Within Limits (PWL) acceptance on FAA pavement work evaluates:
Transverse contraction joints in PCC runway pavement are provided mainly to:
Initial saw-cutting of PCC contraction joints should begin:
Curing of newly placed airfield concrete is essential because it:
Airfield PCC mix designs are often accepted based on flexural strength rather than only compressive strength because:
Dowels at transverse joints in airfield concrete pavements primarily provide:
Surface grooving of runway pavement is performed mainly to:
On airfield asphalt paving, longitudinal joints should be constructed so that they are:
A job mix formula (JMF) for P-401 asphalt defines: