A concrete curb inlet is poured 6 feet long, 3 feet wide, and 4 feet deep (solid rectangle for estimating). How many cubic yards of concrete are required (neat)?
- AAbout 1.3 cubic yards
- BAbout 2.7 cubic yards
- CAbout 4.0 cubic yards
- DAbout 8.0 cubic yards