Before a scaffold is used after an event such as a storm, high winds, or impact from an adjacent crane, OSHA requires:
- ANo additional inspection — the regular daily inspection is sufficient
- BA competent person inspection before workers are permitted to use the scaffold again
- CA licensed engineer's assessment and written sign-off
- DA 24-hour waiting period after the event before use