On a project, the Budgeted Cost of Work Scheduled (BCWS/Planned Value) is 500,000 QAR, the Actual Cost of Work Performed (ACWP) is 250,000 QAR, and the Earned Value (EV/BCWP) is 200,000 QAR. What is the Schedule Variance (SV)?
- A250,000 QAR
- B-50,000 QAR
- C-300,000 QAR
- D300,000 QAR