A land development engineer is calculating the earthworks balance for a site. The excavation volume (cut) is 10,000 bank cubic meters (BCM) of clay. If the soil has a compaction shrinkage factor of 10% when placed in the fill area, what compacted volume of fill will this cut produce?
- A9,000 compacted cubic meters (CCM)
- B11,000 compacted cubic meters (CCM)
- C10,000 compacted cubic meters (CCM)
- D12,000 compacted cubic meters (CCM)